To ensure a smooth and successful Academic Program Review (APR), departments should begin planning at least one year before their scheduled site visit. This page outlines the recommended internal timeline, including key milestones and deadlines, to help departments stay on track and meet Arkansas Division of Higher Education (ADHE) requirements.


? Timeline Overview

ADHE expects all documents to be submitted within six weeks of the completed review process or by June 1, whichever comes first. Use the timeline below to work backward from your anticipated site visit date.


Timeframe Action Item Example Date
1 Year Before Site Visit Establish approximate site visit date Feb 15–16, 2020
150 Days Before Submit consultant recommendations to Provost Sept 15, 2019
120 Days Before Secure consultants Oct 15, 2019
60 Days Before Submit draft self-study to Academic Affairs Dec 15, 2019
30 Days Before Send final self-study to consultants Jan 15, 2020
14 Days Before Finalize and send site visit itinerary Feb 1, 2020
Site Visit Conduct site visit Feb 15–16, 2020
30 Days After Receive consultants’ report Mar 15, 2020
Within 30 Days of Report Develop implementation plan and institutional response Apr 15, 2020
Final Submission Deliver all documents to ADHE By June 1, 2020

? Follow-Up Reporting

Timeframe Report Due
1 Year After Implementation May 15, 2021
3 Years After (if needed) May 15, 2023
5 Years After (if needed) May 15, 2025

✅ Tips for Success

  • Build in buffer time for delays and proofreading.
  • Assign a steering committee member to manage website updates.
  • Use the Program Review Timeline Worksheet to customize your department’s calendar.